Are you wondering what is up next for the Cliff Avenue reconstruction in Enderby? Here is the construction schedule!
Note: activities and dates subject to change without notice.
| Week of… | Description of Activity | Progress |
|---|---|---|
| Phase 1 (George Street to Vernon Street) | ||
| April 4 | Mobilization, tree clearing, asphalt milling, start laying water main | |
| April 18 | Finish laying water main, including disinfection, testing, and tie-ins | |
| April 25 | Start laying storm main | |
| May 2 | Finish laying storm main and install catch basins | |
| May 9 | Dig out for subgrade and place gravel | |
| May 16 | Prepare and pour curbs | |
| May 24 | Start digging in growing materials and root barriers for trees | |
| May 30 | Continue to dig in root barriers and irrigation, start preparing sidewalk | |
| June 6 | Prepare and pour sidewalk | |
| June 13 | Complete sidewalk and Paving Preparation | |
| June 20 | Paving, Landscaping, Install furniture, pour concrete plaza | |
| June 27 | Complete landscape planting, install street furniture and garbage receptacles, activate irrigation, open street to vehicles | |
| July 4-15 | Install light standards and gateway piers | |
| Phase 2 (Vernon Street to Bawtree Bridge) | ||
| September 6 | Mobilization, asphalt milling, sanitary sewer main | |
| September 12 | Finish sanitary sewer main and tie-in | |
| September 19 | Start water main | |
| September 26 | Finish laying water main, including disinfection and testing. | |
| October 3 | Water tie-ins, install storm main and catch basins | |
| October 11 | Finish storm sewer, start dig out for subgrade and place gravel | |
| October 17 | Continue digging for subgrade and placing gravel, prep for curbs | |
| October 24 | Install curbs and prep for paving | |
| October 31 | Paving | |
| November 7-end of project | Sidewalks, landscaping and street lights | |
Last Updated on April 2, 2017.
