Cliff Avenue Construction Schedule

Are you wondering what is up next for the Cliff Avenue reconstruction in Enderby? Here is the construction schedule!

Note: activities and dates subject to change without notice.


Week of… Description of Activity Progress
Phase 1 (George Street to Vernon Street)
April 4 Mobilization, tree clearing, asphalt milling, start laying water main
 April 18 Finish laying water main, including disinfection, testing, and tie-ins
April 25 Start laying storm main
May 2 Finish laying storm main and install catch basins
May 9 Dig out for subgrade and place gravel
May 16 Prepare and pour curbs
May 24 Start digging in growing materials and root barriers for trees
May 30 Continue to dig in root barriers and irrigation, start preparing sidewalk
June 6 Prepare and pour sidewalk
June 13 Complete sidewalk and Paving Preparation
June 20 Paving, Landscaping, Install furniture, pour concrete plaza
June 27 Complete landscape planting, install street furniture and garbage receptacles, activate irrigation, open street to vehicles
July 4-15 Install light standards and gateway piers
Phase 2 (Vernon Street to Bawtree Bridge)
September 6 Mobilization, asphalt milling, sanitary sewer main
September 12 Finish sanitary sewer main and tie-in
September 19 Start water main
September 26 Finish laying water main, including disinfection and testing.
October 3 Water tie-ins, install storm main and catch basins
October 11 Finish storm sewer, start dig out for subgrade and place gravel
October 17 Continue digging for subgrade and placing gravel, prep for curbs
October 24 Install curbs and prep for paving
October 31 Paving
November 7-end of project Sidewalks, landscaping and street lights

Last Updated on April 2, 2017.